Appendix

12 Sample GANTT Chart

No

Task

Start/Finish Date

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

1

Project initiation
- Stakeholder consultation

1 Oct-30 Nov

               

2

TOR out to consultants

1 Nov

               

3

Evaluation and selection of consultant

1 Dec

               

4

Budget and plan prepared

15 Jan

               

5

Application submitted to SFF

By 1 Feb

               

6

Management
- Notification to stakeholders

10 Feb

               

7

Project Mgt Committee Meeting no 1

20 Feb

               

8

Invitations to field day 1 out

5 Mar

               

9

Field day 1 held

10 Apr

               

10

Workshop 1 held

20 Apr

               

11

Project Mgt Committee meeting no 2

30 Apr

               

12

Progress report submitted

15 May

               

Contents | Appendix 13