Appendix
12 Sample GANTT Chart
No |
Task |
Start/Finish Date |
Oct |
Nov |
Dec |
Jan |
Feb |
Mar |
Apr |
May |
1 |
Project initiation |
1 Oct-30 Nov |
||||||||
2 |
TOR out to consultants |
1 Nov |
||||||||
3 |
Evaluation and selection of consultant |
1 Dec |
||||||||
4 |
Budget and plan prepared |
15 Jan |
||||||||
5 |
Application submitted to SFF |
By 1 Feb |
||||||||
6 |
Management |
10 Feb |
||||||||
7 |
Project Mgt Committee Meeting no 1 |
20 Feb |
||||||||
8 |
Invitations to field day 1 out |
5 Mar |
||||||||
9 |
Field day 1 held |
10 Apr |
||||||||
10 |
Workshop 1 held |
20 Apr |
||||||||
11 |
Project Mgt Committee meeting no 2 |
30 Apr |
||||||||
12 |
Progress report submitted |
15 May |